RENEWAL

Shutoko Renewal Project
Haneda Line (Higashi Shinagawa・Samezu) Renewal

PROJECT
OVERVIEW

Renewed structure with excellent long-term durability and maintainability

PROJECT OVERVIEW

Haneda Line (Higashi Shinagawa・Samezu) Renewal is one of the projects planned under the “Shutoko Renewal Project” that is being promoted by Shutoko.
Approximately 1.9 km-long section from near Tennozu Isle Station on Tokyo Waterfront Area Rapid Transit to near Samezu Driver's License Center will be rebuilt with a structure with excellent long-term durability and maintainability.

MAP VIEW OF
RENEWAL
AREA

Plan View

Longitudinal View

The aspect ratio of the longitudinal view is changed to 3:1 ratio, and the height is displayed based on the average sea level height (TP + 0.0 m) of Tokyo Bay. Note that buildings and building height are for illustrative purposes only.

Cross-sectional View

*1 Distance from roadside to revetment *2 Height from the average sea level of Tokyo Bay (TP + 0.0 m) to the road surface

PROCESS

Construction Steps

STEP 1 2016 February

Start of construction
Set up a detour for inbound lanes

STEP 2 2017 September

Switch inbound lanes

2019 September

Reopen Oi JCT

STEP 3 2020 JUNE

Switch outbound lanes
(temporary)

Switch outbound lanes
(completed)

STEP 4

Switch outbound lanes and Oi JCT
(Remove the detour)